Article 6
1. The Commission shall be responsible for the implementation of the specific programme.
2. The procedure laid down in Article 7(2) shall apply for the adoption of the following measures:
- the drawing up and updating of the work programme referred to in Article 5(1), including the instruments to be used on a priority basis and any subsequent adjustment to their use as well as the content of the calls for proposals and the evaluation and selection criteria to be applied;
- approval of funding of RTD actions where the estimated amount of the Community contribution under this programme is equal to or more than EUR 0,6 million;
- the drawing-up of the terms of reference for the external assessment provided for in Article 6(2) of the framework programme;
- any adjustment to the indicative breakdown of the amount as set out in Annex II.