Article 4

1. Member States' management and control systems shall provide an adequate audit trail.

2. An audit trail shall be considered sufficient where it permits:

(a) reconciliation of the summary accounts certified to the Commission with the individual expenditure records and supporting documents kept at the various administrative levels and by the final beneficiaries, including the organisations or firms responsible for implementing projects; and

(b) verification of the allocation and transfers of the available Community and national funds.

An indicative description of the information requirements for a sufficient audit trail is given in Annex II.

3. The responsible authority shall introduce procedures to ensure that a record is kept of the location of all documents relating to particular payments made under the national implementation programme in question and that the documents can be produced for inspection if requested by:

(a) the staff of the authority responsible for handling requests for payment,

(b) the national audit authorities who will carry out the checks required under Article 5(1) of this Decision,

(c) the department or body of the responsible authority entrusted with certifying requests for interim and final payment provided for in Article 17 of Decision 2000/596/EC, and

(d) the officials and authorised representatives of the Commission and the European Court of Auditors.

The officials and agents responsible for controls or those empowered for that purpose may request copies of documents referred to in this paragraph.

4. For a period of five years following the payment by the Commission of the final balance in respect of any project, the responsible authorities shall keep available for the Commission all the supporting documents, i.e. the originals or versions certified to be in conformity with the originals on commonly accepted data carriers, regarding expenditure and checks on the project concerned. This period shall be interrupted in the case of legal proceedings or at the duly motivated request of the Commission.