Article 2
Production at the new hot-wide-strip mill is to be built up to reach a capacity of 900 kt/y only after three years starting at the beginning of 1995.
The capacity limitation at 900 kt/y shall be retained throughout a period of five years following the date of the last closure, or, if later, following the last payment of aid to investment under the current restructuring plan.
Upon the expiry of the aforementioned five-year period another five-year period will start to run, during which the production capacity for hot-wide-strip at EKO Stahl GmbH shall be limited to 1,5 million t/y.
During the first five-year period of capacity limitation Germany shall ensure that the hot-rolled steel capacity to be established at EKO Stahl GmbH will be utilized by the present and future owners exclusively for further processing in EKO Stahl's cold-rolling facilities.
Germany shall ensure that the aid approved pursuant to this Decision is not used to increase the present steel production capacities of EKO Stahl GmbH beyond the planned installation of hot-wide-strip mill bottlenecked at 900 kt/y. There shall be no increase in capacity remaining under the aided restructuring plan, other than resulting from productivity improvements, for a period of five years starting from the date of the last closure, or of the last payment of investment aid under the current restructuring plan, whichever is the later.