Article 2
1. The following definitive closure of production capacity shall be carried out:
- the existing mill for hot-rolled semi-finished products with a capacity of 90 kt/y, the medium-section mill with a capacity of 170 kt/y and the light-section mill with a capacity of 80 kt/y shall be closed down and replaced by a merchant-bar mill with a capacity of 180 kt/y, parts of which being moved from the BGH plant in Siegen,
- the existing crude-steel production facilities with a capacity of 300 kt/y shall be closed down to be replaced by a new electric arc furnace with a capacity of 200 kt/y.
2. All the capacity closures must be achieved by the end of 1996 at the latest.
3. The finality of the closures referred to in paragraph 1 shall be ensured either by the demolition of the installations concerned or by their disposal by sale outside Europe.
4. The beneficiary company shall not increase its remaining capacity for crude steel and hot-rolled finished products, other than resulting from productivity improvements, for a period of at least five years starting from the date of the last capacity closure under the plan or the date of the last payment of aid in respect of investments under the plan, whichever is the later.