Article 65
Termination by the contractor
65.1. The contractor may, after giving 14 days notice to the contracting authority, terminate the contract if the contracting authority:
(a)
fails to pay the contractor the amounts due under any certificate issued by the supervisor after the expiry of the. time limit stated in Article 53.2; or
(b)
consistently fails to meet his obligations after repeated reminders; or
(c)
suspends the progress of the works or any part thereof for more than 180 days, for reasons not specified in the contract, or not due to the contractor's default.
65.2. Such termination shall be without prejudice to any other rights of the contracting authority or the contractor under the contract. Upon such termination, the contractor shall, subject to the law of the State of the contracting authority, be entitled to immediately remove his equipment from the site.
65.3. In the event of such termination, the contracting authority shall pay the contractor for any loss or damage the contractor may have suffered. Such additional payment shall not exceed a limit which has to be specified in the contract.