Article 14
At the end of each half-year, the monitoring official shall prepare for the Monitoring Committee a report on the state of implementation in Central and Eastern Greece of the subprogramme for which he is responsible, indicating public expenditure, total expenditure and physical indicators, and specifying for each measure the changes as compared with forecasts for the IMP. The report shall make particular reference to measures in respect of which the level of total expenditure in two successive half-yearly reports is 50 % lower than that given in the schedule for the IMP, averaged over the year. Article 15
On the basis of the aforementioned information in particular, the appraisal official on the Monitoring Committee shall submit an annual report to it not later than 31 March of the year following the year in question. Before starting the report, he shall seek the opinion of the chairman of the Monitoring Committee.
The annual report shall discuss:
(a) the progress made towards attaining the socio-economic objectives laid down in the Central and Eastern Greece IMP on the basis of an assessment of the state of implementation and economic impact;
(b) the initiatives needed to secure closer compliance with the Central and Eastern Greece IMP as approved, notably as regards the progress made in implementing it, its socio-economic objectives and its integrated nature;
(c) any changes needed in the definition of the measures to be carried out as described in Annex I to the Central and Eastern Greece IMP in order to promote attainment of the latter's socio-economic objectives;
(d) any changes in the organization and functioning of the various authorities involved which would help to streamline decision-making.
The annual report shall be confidential. It shall be made available to the permanent members of the Monitoring Committee only. At a subsequent meeting, and before the prefects and regional secretaries-general decide on the operations falling within their field of competence, the Monitoring Committee shall discuss the operational proposals contained in the annual report, giving its views also on the soundness of the quantitative data and estimates. Where the proposed operations fall within the field of competence of other authorities, the Monitoring Committee shall, under the authority of its chairman, transmit its conclusions to the parties not later than one month following its meeting.
Throughout each year, the monitoring officials shall keep a watch on the implementation of the administrative and legislative measures necessary for the smooth functioning of the programme.