Article 2
The Greek Government shall submit before 1 July every year a progress report on the programme referred to in Article 1.
The report shall state:
- the progress made during the previous calendar year as regards the measures provided for in the programme and set out in Article 1 of Regulation (EEC) No 619/84,
- the location of the irrigation work referred to in Article 1 of Regulation (EEC) No 619/84 and the area served by each individual project,
- expenditure incurred during the calendar year concerned accompanied by the proof referred to in Article 20 (1) of Regulation (EEC) No 1975/82, specifying the sources of finance used,
- in the event of failure to implement or complete the measures provided for in the programme, detailed explanations for such failure.