Art. 55 · 92/97/EEC: Council Decision of 16 December 1991 adopting the general regulations, general conditions and procedural rules on conciliation and arbitration for works, supply and service contracts financed by the European Development Fund (EDF) and concerning their application in the association of the overseas countries and territories (OCT) with the European Economic Community

EU-Recht · · Quelle: EUR-Lex · In Kraft

In EUR-Lex öffnen
Schriftgröße: 100 %

Article 55

Claims for additional payment

55.1.   If under the contract there are circumstances which the contractor considers entitle him to additional payment, the contractor shall:

(a)

if he intends to make any claim for additional payment, give to the supervisor notice of his intention or make such claim within 15 days after the said circumstances become known to the contractor, stating the reason for his claim; and

(b)

as soon as is reasonably practicable after the date of such notice but not later than 60 days after such notice, unless otherwise agreed by the supervisor, submit to the supervisor full and detailed particulars of his claim. In any event, such particulars shall be submitted no later than the date of submission of the draft final statement of account. The contractor shall thereafter promptly submit such further particulars as the supervisor may reasonably require to assess the validity of the claim.

55.2.   When the supervisor has received the full and detailed particulars of the contractor's claim that he requires, he shall, without prejudice to Article 21.4, after due consultation with the contracting authority and, where appropriate, the contractor, determine whether the contractor is entitled to additional payment and notify the parties accordingly.

55.3.   The supervisor may reject any claim for additional payment which does not comply with the requirements of Article 55.