Article 8
Project selection
However, where resources allow, further projects may be funded while maintaining the balance between CCS and RES demonstration projects.
Where no more than two proposals are submitted in a given subcategory, the Commission shall assess the possible impact of the limited number of proposals on the competition for selection under this Decision, and may, where appropriate, decide to postpone award decisions in the relevant subcategory to the second round of calls for proposals.
For the purposes of the first subparagraph, cost-per-unit performance shall be calculated as the sum of the amounts specified in Article 5(3)(b) and (c), divided by the total projected amount of CO2 stored in the first 10 years of operation for CCS demonstration projects, or, the total projected amount of energy produced in the first 5 years of operation for the RES demonstration projects.
Where the relevant Member States confirm, pursuant to Article 5(5), that there is a sufficient public funding for CCS demonstration projects, the highest ranked projects shall be selected in order of their ranking, provided all the following criteria are met:
at least one project and at most three projects are selected in each project category;
at least three projects with hydrocarbon reservoir storage are selected;
at least three projects with saline aquifer storage are selected.
Where those criteria are not met, the project under consideration for selection shall not be selected, and the next highest ranked project shall be considered for selection. The procedure shall be repeated until eight projects are selected.
Where the relevant Member States confirm, pursuant to Article 5(5), that there is a sufficient public funding for RES demonstration projects, the highest ranked project in each subcategory shall be selected. Where, in either of the rounds for calls for proposals there are no eligible and financially and technically viable projects in one or more project subcategories, a corresponding number of additional projects shall be funded in other subcategories of the same project category. Details shall be specified in the call for proposals pursuant to Article 5(1).
The selected CCS demonstration projects shall collectively constitute ‘the CCS group’ and the selected RES demonstration projects shall collectively constitute ‘the RES group’.
For each of the groups, the project representing the highest cost-per-unit performance shall be deselected first, the project representing the highest cost-per-unit performance in another category shall be deselected next. The procedure shall be repeated until the requested funding is covered by the available funds.
However, the first subparagraph shall not apply to transboundary projects.