Article 5
Selection procedure
However, where a project is intended to take place on the territory of several Member States (hereinafter a ‘transboundary project’), the Member State receiving the funding application shall inform the other Member States concerned thereof and shall cooperate with the other Member States with a view to reaching a common decision on the submission of the project by the Member State receiving the funding application.
When submitting proposals for funding, the Member State shall provide the following information for each project:
the relevant costs, in euro, referred to in Article 2(3);
the total request for public funding in euro, which is the relevant costs minus any contribution to those costs from the operator;
the best estimate of the net present value of additional benefits resulting from support schemes as calculated according to Article 3(5);
for CCS demonstration projects, the total projected amount of CO2 stored in the first 10 years of operation, or, for RES demonstration projects, the total projected amount of energy produced in the first 5 years of operation.
Member States shall also notify the Commission of any financing for the project involving State aid pursuant to Article 108(3) of the Treaty so as to allow coordination of the selection procedure with the State aid assessment.
Where that assessment has been concluded positively, the EIB shall, in accordance with Article 8, make recommendations for award decisions to the Commission.